gantt
title Plan de entrega del MVP — YMS JCBM
dateFormat YYYY-MM-DD
axisFormat %b %Y
section Fundamentos
Setup infraestructura + auth :h1, 2026-06-01, 60d
Modelo de datos + CQRS :h1b, after h1, 30d
section Hito 1 — Catálogos y captura básica
Catálogos cerrados :h2, after h1b, 30d
Frontend bootstrap :h2b, after h2, 30d
section Hito 2 — Captura QR de hoja de salida
QR de hoja de salida + sellos :h3, after h2b, 60d
Inspección 360° :h3b, after h3, 30d
section Hito 3 — Integración GPS Samsara
Webhook Samsara + worker async :h4, after h3b, 60d
Anomalías GPS :h4b, after h4, 30d
section Hito 4 — Rondín y caseta
Modo caseta :h5, after h4b, 30d
Rondín de zonas :h5b, after h5, 30d
section Hito 5 — Editor + hardening
Editor de zonas :h6, after h5b, 30d
Observabilidad + compliance :h6b, after h6, 60d
section Producción
UAT con cliente :uat, after h6b, 30d
Go-live :prod, after uat, 14d